front, side & rear extension
|
|
Our Client required C.P.F.M to
build an extension that was to be the size of a house
in its own right. The extension comprised a
living area, two good-sized bedrooms with en-suite
facilities and two standard bedrooms. The image to the
right shows the property prior to works commencing while
the image below and to the left illustrates one of the
en-suite bathrooms |
 |
|
|
 |
The Client was
on a tight deadline and gave C.P.F.M a target completion
period of no longer than five months. Even to C.P.F.M's
standards this was a challenging request but a promise was
made to the Client that all efforts would be made to
complete the project within their specified timeframe. |
|
The image above and the one to
the right shows
the newly created en-suite bathroom. The
works included full tiling to walls and floor, sanitary
ware comprising shower cubicles baths and toilet. |
 |
|
|
 |
After eighteen weeks the project
was completed. Needless to say the Client was
overjoyed with not only the quality of the workmanship but
also with the speed within which the project had been completed.
The image to the left shows the completed extension. |
|